| DATE | CLIENT | PROJECT & OWNER | EQUIPMENT | COUNTRY |
|---|---|---|---|---|
| 2011 August | Aker Solutions | EKOFISK 2/42 Wellhead Platform | 4 * EX EOT Cranes | |
| 2011 August | SK Engineering & Construction | New Booster Station BS-132 & Enhancements to BS-131 KOC |
EX EOT Cranes Jib Cranes EX Electric Hoists SP Manual Hoists |
|
| 2011 July | Aker Solutions | EKOFISK 2/42 Wellhead Platform | 6 * EX EOT Cranes | |
| 2011 July | Bechtel | Australia Pacific LNG Project | 4 * 64t EOT Cranes 12 * Wall Mounted Jib Cranes |
|
| 2011 June | Petrofac Engineering & Construction | Effluent Water Injection PH-1 & Seawater Injection PH-2 KOC |
EX EOT Cranes SP Manual Hoists |
|
| 2011 April | Petrofac International | EPIC for Gas Sweetening Facilities Project, QP | 3 * EX EOT Cranes 7 * SP Manual Hoists |
|
| 2011 April | Petrofac Engineering & Construction | ADCO ASAB FFD Project | Jib Cranes Geared Trolleys |
|
| 2011 March | Bechtel | Queensland Curtis LNG Project | 4 * 64t EOT Cranes 12 * Wall Mounted Manual Jib Cranes |
|
| 2011 March | Petrofac International Ltd | Installation of Fuel Gas & Gas Oil Pipelines & Pumping Station; MAA Azzour & Shuaiba Power Stations | 8 * 10t EOTC 1 * 12.5t EOTC 1 * 5t EOTC |
|
| 2011 February | National Petroleum Construction Co | Qusahwira Full Field Development 1.8 MMBOPD Project ADCO |
Manual Jib Cranes | |
| 2011 January | Petrofac E&C International | Ruwais 4th NGL Train Project | 4 * 5t EOTC 2 * 50t EOTC 1 * 70t EOTC 2 * 8t EOTC 3 * 16t EOTC |
|
| 2010 December | Cristal | 6th Oxidation Line Project | Cranes Hoists |
|
| 2010 October | Hyundai Heavy Industries Co. Ltd | IGD-DAS Island Project ADGAS |
3 * 10t EX EOT Cranes - 13.2m Span | |
| 2010 September | Worley Parsons | Sakhalin 1 Project Arkutun-DAG1 | 2 * 100t EX EOT c/w Cranes - 20m Span | |
| 2010 August | Petrofac Engineering & Construction | Kauther Depletion Compression Project | 10t EX EOT Crane - 13m Span 2 * 20t EX EOT Cranes - 19m Span |
|
| 2010 August | Stahl/PSN | ExxonMobile | 2 * 30t c/w EX Cranes | North Sea |
| 2010 April | Linde Engineering | Borouge 3 | 4 * EX EOT Cranes | |
| 2010 March | M.W.Kellogg | Gorgon Downstream LNG Project | 6 * 100t EX EOT Cranes | Barrow Island |
| 2010 January | Petrofac Engineering & Construction | El Merk Project Central processing Facility and Telecom |
EX EOT Cranes HOT Cranes |
|
| 2009 December | Petrofac Engineering & Construction | ADCO ASAB FFD Project | EX EOT Cranes HOT Cranes Manual Monorail Hoists |
|
| 2009 November | JGC Corporation | Rhourde Nouss CTH Project | EX EOT Cranes Manual Monorail Hoists |
|
| 2009 October | J. Ray McDermott Eastern Hemisphere | Platong Gas II Project | Mechanical Handling Package | |
| 2009 September | Petrofac E&C International | Jihar Stage 3 Project Hayan Petroleum Co |
EX EOT Cranes HOT Cranes & Manual Hoist |
|
| 2009 September | SK Engineering & Construction (GS Corp) | BAB Gas Compression Project ADCO |
EX EOT Cranes Manual Hoist |
|
| 2009 August | Stahl Crane Systems | Sheringham Shoal Offshore Windfarm Platforms Wood Groups |
EOT U/S Cranes | |
| 2009 August | Petrofac International Ltd | 40 inch Gas Pipeline from BS-131 to LPG Plant at MAA | EOT Cranes and manual Hoists | |
| 2009 August | Cristal | Cristal | EOT U/Slung Crane | |
| 2009 July | Parkburn Engineering | FPSO | EOT U/Slung Crane | |
| 2009 July | GS Engineering & Construction | Green Diesel Project | EOT Cranes & Manual Hoist | |
| 2009 July | Loch Lomond Distillers c/o Moulson Process Plant | Loch Lomond Distillers | Pneumatic Crane | |
| 2009 April | Stahl Crane Systems | Total OFON | EX EOT Cranes | |
| 2009 February | Punj Lloyd Limited | EPIC for Strategic Gas Pipeline | EOT Cranes and Manual Hoists | |
| 2009 February | Dodsal | Ruwais Sulphur Expansion Project ABCD |
EX Electric Hoists | |
| 2009 February | KBR | Skida Project | EX EOT Cranes | |
| 2009 January | Saipem s.a | Sonatrach Hassi Messaoud UTBS | EX EOT Cranes SP HOT Cranes |
|
| 2009 January | Worley Parsons | SAKHALIN-1 AD TOPSIDES SAKHALIN |
2 * 100t EX EOT Cranes | |
| 2008 October | Tecnicas Reunidas | Borouge 2 Project | EX EOT Cranes | |
| 2008 September | Petrofac International | Ebla Gas Project | EX EOT Cranes SP HOT Cranes |
|
| 2008 April | SK Engineering & Construction | GC-24 Project KOC |
EX EOT Cranes | |
| 2008 April | Linde Engineering | Borouge 2 Project GASCO |
EX EOT Cranes | |
| 2008 April | Petrofac International | In Salah Gas Project | SP Manual Monorail Hoists | |
| 2008 February | Petrofac International | Harweel Cluster Phase 2 Development Project PDO |
SP Manual Monorail Hoists | |
| 2008 January | Saipem s.a | Swamp Area Gas Gathering for N-LNG Trains 4 & 5 Gas Supply OBRIKOM Gas Plant |
2 * EX EOT Cranes 2 * EX U/S EOT Cranes |
|
| 2008 January | Aker Kvaerner | Skarv Idun Project BP Norge AS |
1 * 25t EX Electric Semi-Goliath Crane | |
| 2007 November | Petrofac International | 4th Stabilization & Seetening Train Karachaganak |
EX EOT Cranes Manual Monorail Hoists |
|
| 2007 November | CB&I Southern Tropic Material Supply | Chilean LNG Project | 3 * EX EOT Cranes | |
| 2007 October | Worley Parsons / Sakhalin Energy / Parsons E&C | Sakhalin II Project, Onshore Processing Facility | Mechanical Handling Package | |
| 2007 July | Tecnimont | KPPC Aromatics Project | 2 * EX EOT Cranes | |
| 2007 June | SK Engineering & Construction | KPPC Aromatics Project KPPC |
6 * EX EOT Cranes 4 * SP HOT Cranes 2 * Electric Hoists 8 * Manual Monorail Hoists |
|
| 2007 May | M.W.Kellogg | Pearl GTL Project | 6 * 65t EX EOT Cranes | |
| 2007 May | Saipem s.a | Sakhalin II Project, Onshore Processing Facility | 9 * Free Standing Jib Cranes c/w Hook Suspension Hoists | |
| 2007 April | Petrofac International | Harweel Cluster Phase 2 Development Project | 4 * EX EOT Cranes 9 * HOT Cranes 9 * EX Electric Monorail Hoists 6 * SP Manual Monorail Hoists |
|
| 2007 April | GS Engineering & Construction | Egypt LAB Project | 2 * EX EOT Cranes 4 * Runway Beams c/w EX Electric Mono Hoists and Manual Mono Hoists |
|
| 2007 April | GS Engineering & Construction | Egypt LAB Project | 2 * EX DG EOT Crane 4 * Runway Beams with EX Electric Mono Hoist 3 * Manual Mono Hoists |
|
| 2006 November | CB&I John Brown | South Hook LNG Terminal | Post Mounted Jib Crane | |
| 2006 November | Eastern Bechtel | AGD III GASCO |
12 * EX EOT Cranes | |
| 2006 November | Bechtel / Reliance | Reliance Jamnagar Export Refinery Project | 34 * EX EOT Cranes 4 * EX US EOT Cranes |
|
| 2006 September | Eastern Bechtel | AGD Phase II Project GASCO |
2 * EX Jib Cranes | |
| 2006 August | Fluor Mideast Ltd | Habshan Gas Complex Expansion Project GASCO |
3 * EX EOT Cranes 3 * EX Jib Cranes |
|
| 2006 July | Eastern Bechtel | OGD Phase III Project GASCO |
4 * EX Jib Cranes 5 * EX Tirfors 15 * Electric Monorail Hoists 26 * SP Manual Monorail Hoists |
|
| 2006 July | KBR / BP Exploration Delta | Saqqara Project | Mechanical Handling Package | |
| 2006 July | Eastern Bechtel | OGD Phase III Project GASCO |
16 * EX EOT Cranes | |
| 2006 May | SK Engineering & Construction | Facilities Upgrade & Relocation Project KOC |
16 * EX EOT Cranes 28 * EX Electric Mononrail Hoists 40 * SP Manual Monorail Hoists |
|
| 2006 April | Hyundai Heavy Industries Co. Ltd | Crude Export Facilities Project KOC |
8 * EX EOT Cranes | |
| 2006 April | JGC Corporation | Rabigh Olefin Plant Project PETRORABIGH |
4 * EX EOT Cranes 1 * EX Electric Monorail Hoist |
|
| 2006 March | Petrofac International | Facilities Upgrade & Relocation Project KOC |
9 * EX EOT Cranes 12 * Electric Monorail Hoists 6 * Manual Monorail Hoists |
|
| 2006 February | Worley Parsons / Sakhalin Energy | Sakhalin II Onshore Processing Facility | 1 * EX Post Mounted Jib Crane 3 * SP Manual Hoists |
|
| 2005 December | CB&I John Brown | South Hook LNG Terminal | 3 * DG EX EOT Cranes | |
| 2005 December | Dodsal | Inter Refineries Pipeline for Takreer | 3 * EX DG EOT Cranes | |
| 2005 September | Petrofac International | Kashagan Field Development Experimental Program Project AGIP,KOC |
7 * EX DG EOT Cranes 2 * SG HOT Cranes 18 * SP Manual Hoists |
|
| 2005 July | Technip | BAPCO Low Sulphur Diesel Production Project | 2 * 2t SG EX EOT Cranes 2 * 5t SG EX EOT Cranes |
|
| 2005 April | BP Angola c/o KBR | Greater Plutonio Project BP |
Mechanical handling Package | |
| 2005 March | GS Engineering & Construction | QP LAB Project | 18 * SP Manual Monorail Hoists 3 * EX Elec Monorail Hoists 2 * EX DG EOT Cranes 2 * SG EOT Cranes |
|
| 2005 March | JGC Corporation | BAPCO Low Sulphur Diesel Production Project | 1 * EX SG EOT Crane 2 * SP Hand Geared Trolleys |
|
| 2004 August | Petrofac International | EPIC of Rag & Flare Mitigation Integrated Project | 1 * 2t EX EOT Crane 6 * 1t EX Electric Hoists c/w Hand Geared Trollies |
|
| 2004 January | M.W.Kellogg | Sonatrach in Amenas Gas Project BP |
6 * EX DG EOT Cranes 3 * DG EOT Cranes 1 * SG U/S EOT Crane with Electric Chain Hoist |
|
| 2003 October | Linde AG Engineering | Hammerfest LG Plant Statoil |
6 * EX EOT Cranes 2 * EX Jib Cranes 30t EX Portal Crane |
|
| 2003 September | R. Stahl Ltd | Qalhat LNG Project | 5t EX Pneumatic SG Overhead Travelling Crane | |
| 2003 July | KSB Fluid Systems GmbH | Bengasi Coveyance Pump Station | 20t DG EOT Crane 6 * Low Headroom Manual Monorail Hoists 2 * Underbraced Jib Cranes |
|
| 2003 June | Samsung Corporation | New LPG Tank project | 1 * 20t EX DG EOT Crane 2 * 3.5t EX Short Headroom Electric Monorail Hoists |
|
| 2003 May | Hyundai Heavy Industries Co. Ltd | Bonny Terminal Integrated project | 5 * 10t EOT Crane 4 * EX EOT Cranes 1 * 20t EOT Crane 5 * 5t EX Monorail Hoists |
|
| 2003 April | PFD (UK) Ltd | TCO Asset Development Project | 1 * 40/5t EOT Crane 2 * 8t EOT Cranes |
|
| 2003 April | Petrofac International | AGT Pipelines & Facilities Project | 3 * 10t EX EOT Cranes 3 * 10t EOT Cranes 3 * HOT Cranes 3 * Manual Trolley Hoists 6 * 5t SP HOT Cranes |
|
| 2003 April | SEMBCORP Simon Carves | 3161 M - LDPE Plant | 2 * 12t EOT Cranes | |
| 2003 February | GEIE Saipem-BOS | ROD Integrated Development Project | 2 * EX EOT Cranes 1 * EOT Crane |
|
| 2003 January | NPCC / TECHNIP / NSQ | Soroosh & Nowrooz Integrated Development Project | 40 * SP Manual Hoists c/w Geared Trolley & Elec Hoist c/w manual Trolley | |
| 2002 October | Stone & Webster | BASF - YPC Project | 2 * 6t EX Bridge Crane 1 * 8t SP HOT Crane |
|
| 2002 September | Inco Australia Managment Pty | Goro Nickel Project Bechtel / Technip JV |
14 * Elec Top Running Travelling Crane | |
| 2002 September | Larsen & Toubro | MNW Process Platform Project ONGC |
1 * Bridge Crane 2 * Manual Chain Hoists 3 * Electric Wire Rope Hoists |
|
| 2002 September | Daewoo E&C Co. Ltd | Cawthorn Channel AG Gathering Project | 2 * DG EOT Cranes | |
| 2002 August | PFD (UK) Ltd | TCO Asset Development Project | 2 * EX EOT Cranes 2 * EX Electric Monorail Hoists |
|
| 2002 August | M.W.Kellogg / Damietta Project Managment Co. | Damietta Egypt LNG Project - 019 | 14 * EX EOT Cranes | |
| 2002 May | Bechtel USA | Spalding Energy Project | 1* 95/20t EOT Crane - 27M Span and 24.5M Height of Lift |
|
| 2001 November | Simon Carves | Cristal T102 Pigment Expansion project | 5 * Monorail Manual Electric Chain Hoists 2 * Electric US Cranes |
|
| 2001 November | M.W.Kellogg | In Salah Gas Project | 6 * D/G EOT Crane | |
| 2001 October | Petrofac International | Upgrading of Gathering Centre 23 KOC |
2 * 5t SP S/G HOT Cranes | |
| 2001 September | Petrofac International | Kharyage Field Development Phase 2 Total Exp Production |
5t SG HOT Crane | |
| 2001 August | Kuwait Controls Co | Combined Weapons Station KOC |
4 * SG EOT Cranes 4 * SG Electric U/Slung Cranes |
|
| 2001 July | R. Stahl Ltd | Al Khadra Puping Station project | 4 * Elec Top Running Cranes & 6 * Elec Monorail Chain Hoists | |
| 2001 June | GROOTINT BV | Ringhorne Development | 2 * 15t EX Pneumatic Head Cranes 1 * 2t EX Gantry |
|
| 2001 February | Larsen & Toubro | HRC Process Platform ONGC |
1 * 12.5t EX EOT Crane 4 * Manual Hoists |
|
| 2001 February | Marathon Oil UK Ltd | East Brae Modification on gantry Crane Amec & Mobil |
2 * EX Manually Operated S/G U/Slung Travelling Crane | |
| 2001 January | JGC Corporation | Urhoud Project | 11 * EX Gantry Cranes | |
| 2001 January | Qatar Kentz (W.L.L) | Halul Island Power Generation | 20t EX D/G EOT Crane | |
| 2000 December | SADRA - Samsung Consortium/BP | South Pars | Explosion Proof Gantry Cranes & Hoists | |
| 2000 September | Hyundai Engineering & Construction | NGL-4 EPC Project QGPC |
6 * EX Electric Bridge Cranes 2 * c/w Hoists & Trolleys |
Mesaieed, Dukan |
| 2000 September | Getco Engineering Co. Ltd | Yibal Expansion Project PDO |
1 * 3.2t SP EX SG EOT Crane | |
| 2000 August | Samsung Heavy Industries | Cakarawala Gas Development Project CKP Platform |
EX & SP Elec & Manual Monorail Wire Rope Hoists & EX U/Slung EOT Crane | |
| 2000 June | National Petroleum Construction Co | Zero Flaring Project ADOC |
2 * EX Explosion Proof Cranes | |
| 2000 March | GE Energy Products - Europe | KPC Powerstation Karachaganak |
1 * 20t DG EOT Crane 1 * 10t DG EOT Crane |
|
| 2000 February | Al Kauthar International Trading Co | Replacement of Morris Crane in Adu Dhabi | 1 * 5t SG EOT Crane | |
| 1999 November | Technip Contrina | Sincor Downstream Project Contrina |
3 * EX DG Electric Bridge Crane | Jose |
| 1999 June | Alliance Bechtel Linde | Borouge Petrochemicals Project ADNOC |
5 * EX DG EOT Cranes | |
| 1999 February | Stolt Comex Seaway | RPL/RFW Project Ships Crane | 6.2t S/G EOT NHz Ships Crane | |
| 1998 October | Technip / Bechtel JV | OGD ADNOC Phase I&II | 12 * Double Box Girder EX EOT Cranes & Hoists | |
| 1998 June | Bechtel International | Tengizchevroil KTL Refinery | 1 * SP TR HOT Crane 4 * SP US HOT Cranes |
|
| 1998 June | Brown & Root | South Arne Field Development Project | SP Mechanical Handling Equipment (pushed & geared trolleys) | North Sea |
| 1998 March | M.W.Kellogg | Karsto Utbyggingsprosjekt - KUP Statoil |
8 * EX DG EOT Cranes and USlung EOT Crane | |
| 1998 January | Hyundai Heavy Industries Co. Ltd | ONGC BCP, Bombay High | 5 * EX EOT Cranes 8 * EX Electric Wire Rope Hoists 20 * SP c/w Hoists & Geared Trolleys |
|
| 1997 October | Bechtel / Reliance | Jamnagar Refinery | 32 * EX DG EOT Cranes | |
| 1997 August | Bechtel Ltd | Tengizchevoil Refinery Chevron |
2 * 30t EX DG EOT Cranes with Aux Hoists | |
| 1996 December | Bechtel Limited / Arabian Industrial Fibres | IBN Rushd PTA & Aromatics Project | 2 * DG EOT Cranes 3 * SG EOT Cranes 3 * Electric Wire Rope Hoists |
Yanbu |
| 1996 July | Brown & Root | ETAPS (Eastern trough Area Project) | EX Mechanical Handling Package | North Sea |